[edit] Pre Debconf
[edit] End May 2012 (!!)
- Logo and visual design ready, sponsor brochure content outline
- Visual design:
- visual design mumble meeting
- Visual design:
- Sponsoring
- sponsoring levels, ranges
- Facts about Debian and DC13
- rough budget
- ...
[edit] Mid June
- Sponsoring brochure ready for Swiss sponsors (campaign together with DC12)
- mumble meeting (? or in person meeting)
- collect adresses and personal contacts
- send brochures with cover letter about DC12 (in paper)
- start working on migrating debconf-team + -data svn _completly_ to git, that is all past DebConfs
[edit] Begining of August (1-2 weeks after DC12)
- recontact potential sponsors
- if possible phone contacts, ask if they want to sponsor
[edit] August 2012
- Venue secured and dates decided
- contract with venue signed
- prices finalized or at least mostly finalized
- migrate away from pentabarf, possible to frab (https://github.com/oneiros/frab)
- don't do this to early after DC12, so people can still rate events
[edit] October 2012 (? or jan/feb 2013)
- Orgateam week-end
- kick of for concrete orga tasks
- "teambuilding"
- invite some global team members (?)
[edit] October 2012
- start contacting global sponsors
[edit] End 2012
- Enough sponsoring secured to be sure that the conf can happen
- Network connectivity sorted out
[edit] February 2013
- Registration opens
[edit] March 2013
- Registration for sponsored participants closes
- Final budget possible
[edit] April 2013
- Enough sponsoring for everything secured
[edit] Debconf
- <2013-08-05 Mon> DebCamp 13 starts
- <2013-08-11 Son> DebConf 13 starts
- <2013-08-18 Son> DebConf 13 ends
[edit] Post Debconf
[edit] October 2013
- Post debconf team week-end
- Celebrate debconf -> thank you for the organiziers
- Overview of what's still pending
- Finish as much as possible
- Give an energy boost to finish things
- invite interested global team members (?)
[edit] End of October 2013
- final financial report
- All expenses are paid
- Travel and other reimbursement finished
[edit] End of December 2013
- Final report finished